FrieslandCampina (NL)

FrieslandCampina - Industrial Insulation

Tight planning, factory reconstruction within 5 weeks

Scope

Reconstruction of production facility

Challenge

Intensive preparation, good coordination of work such as applying insulating sheeting

Performance

The factory had to be converted and made dust-proof within a maximum of five weeks of the production stop.

In control

We directed the reconstruction of the drying tower. In just three weeks, the cladding was removed, the steel structure strengthened, insulating cladding applied, everything sealed and the entire finishing process took place. All this included the removal and re-installation of the roof.

Completion accomplished successfully

The reconstructed tower was delivered on time at the end of April. Thanks to intense preparation and excellent project management before, during and after construction, this project was successfully completed in several ways.